Stanford Geothermal Workshop · Production Engineering

Production-Injection at the Costa Rica Geothermal Fields 1994 – 2018: Dr. Alfredo Mainieri Protti (Formerly Miravalles) and Pailas

Federico NIETZEN, Leonardo SOLIS

Download PDF (5866 KB) Hosted on pangea.stanford.edu

Abstract

The electricity capacity (from the geothermal resource) installed in Costa Rica is approximately 215 MWe in 2018, increased to 270 MWe with the Pailas II Unit by 2019. There are four steam units installed in the Dr. Alfredo Mainieri Protti field (formerly Miravalles Geothermal Field): Unit 1 (55 MWe, although it can reach 60 MWe, 1994), Wellhead Unit (5 MWe, 1995), Unit 2 (55 MWe, although it can reach 60 MWe, 1998) and Unit 3 (29 MWe, 2000), and also a binary plant: Unit 5 (19 MWe, 2004). Pailas has a binary unit with a production of 42 MWe installed (2011). However, the commercial production of the second unit (Pailas II Unit, steam unit) begins in 2019, with a contribution of about 55 MWe The Dr.Alfredo Mainieri Protti field has supplied the steam and brine needed to generate over twenty four years of exploitation (1994-2018), while Pailas field (Unit I) has approximately seven years of operation, with changes in the configuration of wells. The performance of the fields and changes in strategies, in terms of production-injection, are described in the following sections.

Details

Conference
Stanford Geothermal Workshop
Year
2019
Session
Production Engineering
Paper number
Nietzen2
Language
English
Copyright
Stanford Geothermal Program
Keywords
Production injection Dr. Alfredo Mainieri Protti Miravalles Pailas Costa Rica
Record ID
29062

Suggested citation

Federico NIETZEN, Leonardo SOLIS (2019). Production-Injection at the Costa Rica Geothermal Fields 1994 – 2018: Dr. Alfredo Mainieri Protti (Formerly Miravalles) and Pailas. Proceedings, Stanford Geothermal Workshop 2019, Paper Nietzen2.

Proceedings-level reference. Individual papers do not carry DOIs.

More papers by Nietzen ›