Geothermal Resources Council Transactions · Power plant design and operation; Binary cycle power generat

The McGinness Hills Geothermal Project

Nordquist, Josh; Delwiche, Ben

Download unavailable for this file.

Abstract

The McGinness Hills Geothermal Project was completed in July 2012 and provides 30 MW of base-load renewable power to the NV Energy transmission system. This project was awarded GEA Honors for environmental stewardship (nominated by the Bureau of Land Management) by the Geothermal Energy Association, signifying it as a major accomplishment for Ormat, and the geothermal industry. Geothermal development is no easy task; discovering a geothermal resource is a difficult and risky procedure and developing the project can easily be just as difficult. In this paper we will illustrate both the unique challenges of the McGinness project along with insight on how Ormat is excelling in the art of geothermal development and developing profound technologies continually pushing the industry forward.

Details

Conference
Geothermal Resources Council Transactions
Year
2013
Session
Power plant design and operation; Binary cycle power generat
Language
English
Geographic area
McGinness Hills, Nevada
Copyright
Geothermal Resources Council
Keywords
Nevada McGinness Hills Ormat Ormat Energy Converter OEC Organic Rankine Cycle ORC modular geothermal aircooled NV Energy integrated two-level unit U.S. Department of Energy DOE Bureau of Land Management BLM Nevada Division of Wildlife
Record ID
24704

Suggested citation

Nordquist, Josh; Delwiche, Ben (2013). The McGinness Hills Geothermal Project. Proceedings, Geothermal Resources Council Transactions 2013.

Proceedings-level reference. Individual papers do not carry DOIs.

More papers by Nordquist, Josh; Delwiche, Ben ›