World Geothermal Congress · 21. Drilling and Completion Technology

An Effective Well Development Method for Deep Screen Completed Wells

Jan-Erik Rosberg

Abstract

In Lund, Sweden productivity problems were encountered during flow testing of a 1927 m deep gravel packed screen completed well and it became apparent that well development was needed to increase productivity. A hydro-jetting system using coiled tubing in combination with simultaneous pumping was developed and tested and found to be successful. To verify whether the well development improved the well, the results of a pumping test conducted before and after the jetting operation were compared. In addition flowmeter logging during the jetting operation was also used to verify the improvements. Hydro-jetting in combination with simultaneous pumping proved to be an effective cleaning method. After 100 minutes of pumping, there was approximately 110 m less drawdown and 15 l/s higher average flow rate compared to the values before the jetting operation. Influence of wellbore storage was significant during the flow tests carried out before the well development, but was negligible thereafter.

Details

Conference
World Geothermal Congress
Year
2010
Session
21. Drilling and Completion Technology (29 papers)
Paper number
2119
Language
English
Geographic area
Lund, Sweden
Copyright
International Geothermal Association
Keywords
Well development hydro-jetting coiled tubing
Record ID
6360

Suggested citation

Jan-Erik Rosberg (2010). An Effective Well Development Method for Deep Screen Completed Wells. Proceedings, World Geothermal Congress 2010, Paper 2119.

Proceedings-level reference. Individual papers do not carry DOIs.

More papers by Rosberg ›