New Zealand Geothermal Workshop · Geothermal Engineering - Production and Management

Additional Wellhead Units at Ulumbu, Indonesia

Mendive, David ., Heninger, Milan ., Geffert, Sean . and Hamacek, Yvette

Abstract

Geothermal Development Associates (GDA) provided engineering, major equipment, and startup and commissioning services to PT Perusahaan Listrik Negara (Persero) (PLN) for a modular 2 x 2.5 MW geothermal wellhead plant located at Ulumbu, Flores Island, Indonesia. PT Rekadaya Elektrika (Rekadaya) constructed the plant under a separate contract with PLN. The plant was commissioned in August 2014. GDA also provided construction support and training for PLN personnel. The new units, supplied by GDA, are the 3rd and 4th units installed at Ulumbu, which are all served by the same dry steam production well, ULB-2, drilled in 1994.

Details

Conference
New Zealand Geothermal Workshop
Year
2014
Session
Geothermal Engineering - Production and Management
Paper number
116
Language
English
Geographic area
Ulumbu, Indonesia
Copyright
University of Auckland
Keywords
Geothermal power wellhead power plant small scale dry steam expansion non-condensing Ulumbu Flores Island Indonesia GDA Geothermal Development Associates PT PLN (Persero) PT Perusahaan Listrik Negara (Persero) Rekadaya Elektrika
Record ID
20296

Suggested citation

Mendive, David ., Heninger, Milan ., Geffert, Sean . and Hamacek, Yvette (2014). Additional Wellhead Units at Ulumbu, Indonesia. Proceedings, New Zealand Geothermal Workshop 2014, Paper 116.