World Geothermal Congress · 13. Power Generation

Rehabilitation and Modernization Project for Unit 5 of Cerro Prieto Power Plant

Ismael Canchola Felix

Abstract

This project includes the increase of steam production in the field using the surplus energy from the separated water as the repowering of the Unit 5 rated 30 MW. This repowering considers the cooling tower substitution, turbine rehabilitation and non condensable gas extraction system.

Details

Conference
World Geothermal Congress
Year
2005
Session
13. Power Generation (26 papers)
Paper number
1318
Language
English
Geographic area
Cerro Prieto, Mexico
Copyright
International Geothermal Association
Keywords
Units modernization and rehabilitation Residual energy utilization Secondary steam utilization Efficiency improvement Cerro Prieto
Record ID
1159

Suggested citation

Ismael Canchola Felix (2005). Rehabilitation and Modernization Project for Unit 5 of Cerro Prieto Power Plant. Proceedings, World Geothermal Congress 2005, Paper 1318.

Proceedings-level reference. Individual papers do not carry DOIs.