  1. Repowering of the Cove Fort Power Plant

    Sacerdoti, Ariel · Geothermal Resources Council Transactions · 2013 ·Power plant design and operation; Binary cycle power generat

    … in 2007. The resource characteristics were evaluated for repowering the power plant and several alternatives were considered in order to maximize the owner?s return on investment (ROI). Namely, the design objective was to maximize generation output given …

    View paper: Repowering of the Cove Fort Power Plant Download unavailable

  2. Expansion and Repowering of Mammoth Geothermal Resource: Selection of Generation Cycle and Expander Technology

    Buchanan, Tom; Nickerson, Larry · Geothermal Resources Council Transactions · 2011 ·Power plant design and operation; Organic Rankine cycle; Iso

    … and developed. Based on successful experience gained in repowering and expansion of the Steamboat complex, a plan has been developed to replace the existing aging generating plants with two new higher efficiency Ormat plants. The new Ormat units will …

    View paper: Expansion and Repowering of Mammoth Geothermal Resource: Selection of Generation Cycle and Expander Technology Download unavailable

  3. Repowering Steamboat 2 and 3 Plants with New Axial Flow Turbines

    Tom Buchanan, Wade Posten, Sean Berryman · World Geothermal Congress · 2010 ·26. Power Generation

    … with axial flow Ormat engineered turbines. The plant repowering was completed in mid 2008. The repowering was successfully performed with minimal plant down time using cross-functioning teams. The project required coordinated planning utilizing …

    View paper: Repowering Steamboat 2 and 3 Plants with New Axial Flow Turbines PDF: Repowering Steamboat 2 and 3 Plants with New Axial Flow Turbines (1425KB)

  4. Repowering Steamboat 2 and 3 Plants with New Axial Flow Turbines

    Buchanan, Tom; Posten, Wade; Berryman, Sean · Geothermal Resources Council Transactions · 2009 ·Turbines; Isobutane; Operations management

    … with axial flow Ormat engineered turbines. The plant repowering was completed in mid 2008. The repowering was successfully performed with minimal plant down time using cross-functioning Ormat teams. The project required coordinated planning utilizing …

    View paper: Repowering Steamboat 2 and 3 Plants with New Axial Flow Turbines Download unavailable

  5. Geothermal power plant repowering by means of biomass combustion

    Fedeli, Moscariello, Sabatelli · European Geothermal Conference · 2013 ·6 Hydrothermal Systems – Applications (HS2-4)

    The idea of increasing both the power output and the thermal efficiency of geothermal steam cycles by means of steam superheating has a long history. However, most (if not all) evaluations carried out so far, including a previous Enel study, dealt with fossil …

    View paper: Geothermal power plant repowering by means of biomass combustion PDF: Geothermal power plant repowering by means of biomass combustion (253 KB)

  6. Repowering eines im vierten Jahrzehnt durch Erdwaermesonden nachhaltig genutzten Standortes in Schoenaich (Kreis Boeblingen)

    E. Moegele · Der Geothermiekongress · 2010

    Die fruehesten bislang dokumentierten Erdwaermesondenborhungen in Mitteleuropa wurden von der Gungl-Bohrgesellschaft, Renningen, im Spaetsommer 1974 in Schoenaich (Kreis Boeblingen) ausgefuehrt. Fuer die Umruestung eines bestehenden Gebaedes zur monovalenten …

    View paper: Repowering eines im vierten Jahrzehnt durch Erdwaermesonden nachhaltig genutzten Standortes in Schoenaich (Kreis Boeblingen) No PDF on file

  7. Repowering Back Pressure Turbines at the Los Humeros Geothermal Field

    Vega, Guillermo De La Torre · Geothermal Resources Council Transactions · 1994 ·Power plant design and operation

    View paper: Repowering Back Pressure Turbines at the Los Humeros Geothermal Field Download unavailable

  8. The 26 MW Cove Fort Geothermal Power Plant

    Sacerdoti · European Geothermal Conference · 2013 ·6 Hydrothermal Systems – Applications (HS2-4)

    … in 2007. The resource characteristics were evaluated for repowering the power plant and several alternatives were considered in order to maximize the owner’s return on investment (ROI). Namely, the design objective is to maximize generation output given …

    View paper: The 26 MW Cove Fort Geothermal Power Plant PDF: The 26 MW Cove Fort Geothermal Power Plant (531 KB)

  9. Increasing Electric Power Output from Single-Flash Geothermal Plants

    Rosenblatt, J. H.; Saulson, S. H. · Geothermal Resources Council Transactions · 1990 ·Single flash; Power plant design and operation; Flash steam

    Single flash geothermal power plants are relatively inefficient compared to their higher temperature "cousins." The Low Temperatures Engine System (LTES) is a novel cycle applicable to many types of power plants. The LTES has been analyzed as an add on …

    View paper: Increasing Electric Power Output from Single-Flash Geothermal Plants Download unavailable

Papers are freely accessible. Copyright remains with the authors and conference organisers as stated on each paper.