Title Raft River 5-MW(e) Geothermal Pilot Plant Project
Authors Rasmussen, T. L.; Whitbeck, J. F.
Year 1980
Conference Geothermal Resources Council Transactions
Keywords Power Generation; Well Pumps; USA; Idaho; Raft River; Pilot Plant; Dual boiling power cycle; Isobutane; Evaluation; Submersible well pumps
Abstract The Raft River 5-MW(e) Pilot Plant Project was started in 1976. Construction is scheduled for completion in July 1980, with three years of engineering and operation testing to follow. The plant utilized a 280°F geothermal fluid energy source and a dual boiling isobutane cycle. Developmental efforts are in progress in the areas of downhole pumps and chemical treatment of geothermal fluids for cooling tower makeup.